United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

SOLAR + STORAGE Β· MISO

Solar + storage project J2776, Fulton County

Solar + storage project J2776, Fulton County is a 10.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Fulton County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2776
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
WINAMAC to BRUCE LAKE 69kV (Circuit ID 6913) NIPSCO AREA
Location
Fulton County, Indiana
Technology
Solar: 10.0 MW Β· Battery
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
7 September 2022
Proposed online date
January 2025
Withdrawn
March 2023

Location

Marker shows the centre of Fulton County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem