Onshore wind project G887, Benton County

Onshore wind project G887, Benton County is a 20.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Benton County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2007 (completed)
  2. Withdrawn / abandonedFeb 2011 (project stopped here)
  3. ConsentedFeb 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G887
Grid region
MISO (Midcontinent)
Connection point (POI)
Watseka - Goodland 138 kV
Location
Benton County, Indiana
Technology
Wind: 20.0 MW
Total requested
20.0 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
16 October 2007
Agreement signed
7 February 2011
Proposed online date
October 2012
Withdrawn
February 2011

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem