United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

SOLAR Β· MISO

Solar project J492, Montgomery County

Solar project J492, Montgomery County is a 20.0 MW solar request withdrawn in the MISO interconnection queue, in Montgomery County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2015 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J492
Grid region
MISO (Midcontinent)
Connection point (POI)
connection to 69 kV Duke line feeding Cherry Grove substation
Location
Montgomery County, Indiana
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
12 November 2015
Proposed online date
May 2017
Withdrawn
June 2017

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem