Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,138571.6 GW
Active in queue179.2 GW464 requests
Agreement signed81.7 GW215 requests
Withdrawn2,138571.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,138 requests · page 10 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Linwood Solar Farm
Solar + storage
405 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2019
Familia Hybrid Solar
Solar + storage
405 MWWithdrawn / abandoned Maricopa, CACAISO Apr 2019target 2022
Comal Flats 1
Solar + storage
405 MWWithdrawn / abandoned Fresno, CACAISO Apr 2020target 2024
Tava Flats
Solar + storage
405 MWWithdrawn / abandoned Fresno, CACAISO Apr 2021target 2024
Altilium Energy Storage
Battery storage
404 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2025
Pelagic Energy Storage
Battery storage
404 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2024
Pisces Energy Storage
Battery storage
404 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Sageberry Solar
Solar + storage
404 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Aquarius Energy Storage
Battery storage
404 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Jaciva Energy Storage
Battery storage
404 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2024
Garces Hybrid Solar
Solar + storage
403 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Agua Amarga Wind
Onshore wind
403 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2023
DRY Grape Hybrid Solar
Solar + storage
403 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Vista Power Project
Gas
402 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2012target 2018
North Highland
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Sheep Mountain
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Hyder Valley Farms
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Box Ranch 1
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
East Mule
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Box Ranch 2
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Shadow Hills
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Sandy Valley
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Ulatis Creek
Solar + storage
401 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Hickory Solar Farm
Solar
400 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2014
Canella 2 Solar Farm
Solar + storage
400 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2020
Siberia Phase I Segs (Fka DPT Broadwell Lake II)
Solar
400 MWWithdrawn / abandoned San Bernardino, CACAISO Jul 2007target 2018
Yellow Hay Hybrid Solar
Solar + storage
400 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2022
DPT Broadwell Lake
Solar
400 MWWithdrawn / abandoned San Bernardino, CACAISO Jan 2007target 2011
Lotus 3
Battery storage
400 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Collomia Storage
Battery storage
400 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Lakey Solar
Solar + storage
400 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2025
Solar + storage project G0868, Modoc County
Solar + storage
400 MWWithdrawn / abandoned Modoc, CAWest Jun 2023target 2026
Hydrogen Energy California
Gas
400 MWWithdrawn / abandoned Kern, CACAISO Feb 2008target 2015
Silkie
Battery storage
400 MWWithdrawn / abandoned Merced, CACAISO Apr 2023target 2031
Amboy
Onshore wind
400 MWWithdrawn / abandoned San Bernardino, CACAISO Sep 2006target 2010
Idris Storage
Battery storage
400 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Patterson Pass GT Project
Gas
400 MWWithdrawn / abandoned San Joaquin, CACAISO May 2008target 2012
Desert Jasper PV
Solar
400 MWWithdrawn / abandoned San Bernardino, CACAISO Nov 2007target 2016
Kramm
Battery storage
400 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Palo Verde Energy Storage
Battery storage
400 MWWithdrawn / abandoned Riverside, CACAISO Apr 2015target 2020
Solar + storage project Q72, San Bernardino County
Solar + storage
400 MWWithdrawn / abandoned San Bernardino, CAWest Jul 2019target 2021
Pavion
Battery storage
400 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2026
Fitzgibbons Solar
Solar + storage
400 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2025
Wellhead Power Kern 3
Gas
400 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Solar project 2, Sacramento County
Solar
400 MWWithdrawn / abandoned Sacramento, CAWest Oct 2019target 2023
Star Generation
Gas
400 MWWithdrawn / abandoned San Diego, CACAISO Apr 2007target 2010
Siberia Phase II Segs (Fka DPT 9)
Solar
400 MWWithdrawn / abandoned San Bernardino, CACAISO Jul 2007target 2015
CPV California II
Gas
400 MWWithdrawn / abandoned San Bernardino, CACAISO Mar 2007target 2010
Soldier Flat
Onshore wind
400 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Solar project Q39, Kern County
Solar
396 MWWithdrawn / abandoned Kern, CAWest Nov 2012target 2015
Page 10 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)