ONSHORE WIND Β· CAISO

Amboy

Amboy is a 400 MW onshore wind request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2006 (completed)
  2. Withdrawn / abandonedOct 2006 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
129
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Pisgah 230kV Substation
Location
San Bernardino County, California
Technology
Wind: 400 MW
Total requested
400 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
13 September 2006
Proposed online date
March 2010
Withdrawn
October 2006

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in San Bernardino County