πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

BATTERY STORAGE Β· CAISO

Idris Storage

Idris Storage is a 400 MW battery storage request withdrawn in the CAISO interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
caiso_c15_326
Grid region
CAISO (California)
Connection point (POI)
Devers 230kV
Location
California
Technology
Battery: 400 MW
Total requested
400 MW
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
January 2026
Withdrawn
December 2024

Location

No county location in the queue data.

Power plants in California Β· Transmission lines in California

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem