Wandylaw
Wandylaw is a 20.5 MW onshore wind farm in North East England, operated by Cubico Sustainable Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- North East
- England
Key facts
- Installed capacity
- 20.5 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Cubico Sustainable Investments
- Region
- North East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- NE67 5HG
- Coordinates
- 55.5196, -1.7642
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Wandylaw compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 20.5 MW station would generate roughly 47 GWh of electricity in a year, similar to the annual use of about 17,290 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in North East All run by Cubico Sustainable InvestmentsNearby generating sites
- Middlemoor Β· 54 MW onshore wind farm2.3 km
- Barmoor Β· 12 MW onshore wind farm22.9 km
- Wingates Β· 15 MW onshore wind farm27.2 km
- North Steads Β· 18.5 MW onshore wind farm29.4 km
- Sisters Β· 8.2 MW onshore wind farm31.3 km
- Lynemouth Power Limited Β· 420 MW biomass power station37.7 km
- Lynemouth Β· 26 MW wind farm38.1 km
- Ray Β· 54.4 MW onshore wind farm42.2 km
Also operated by Cubico Sustainable Investments
Cubico Sustainable Investments operates 18 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- Blue Energy
- Planning authority
- Northumberland
- Planning reference
- 06/B/0765
- Application submitted
- 1 August 2006
- Permission granted
- 10 February 2008
- Construction started
- 30 May 2012
- Began operating
- 30 July 2013
- Capacity in planning record
- 20.5 MW
- Address
- The Ellingham Estate, 3.5km West of the Village of Ellingham, Northumberland
- REPD reference
- 4250
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source