WIND Β· OPERATIONAL

Kelmarsh

Kelmarsh is a 12.3 MW onshore wind farm in East Midlands England, operated by Cubico Sustainable Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • East Midlands
  • England

Key facts

Installed capacity
12.3 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Cubico Sustainable Investments
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
NN6 9LZ
Coordinates
52.3957, -0.9356

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Kelmarsh compares

295th of 488largest wind farms in the UK register
16th of 34in East Midlands
0.04%of listed UK wind farms capacity
β‰ˆ 28 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 12.3 MW station would generate roughly 28 GWh of electricity in a year, similar to the annual use of about 10,380 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East Midlands All run by Cubico Sustainable Investments

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Kelmarsh Wind Farm (Resubmission)
Developer / operator
Blue Energy
Planning authority
West Northamptonshire
Planning reference
DA/2010/0100
Application submitted
8 February 2010
Permission granted
19 December 2011
Construction started
1 April 2014
Began operating
1 July 2016
Capacity in planning record
12.5 MW
Address
Land To The South Of The A14 And North Of Haselbech, Kelmarsh, Northamptonshire, Northamptonshire
REPD reference
4084

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026