WIND Β· OPERATIONAL

Yelvertoft

Yelvertoft is a 16.4 MW onshore wind farm in East Midlands England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • East Midlands
  • England

Key facts

Installed capacity
16.4 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Greencoat Capital
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
NN6 6AS
Coordinates
52.3748, -1.1511

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Yelvertoft compares

251st of 488largest wind farms in the UK register
8th of 34in East Midlands
0.06%of listed UK wind farms capacity
β‰ˆ 37 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 16.4 MW station would generate roughly 37 GWh of electricity in a year, similar to the annual use of about 13,830 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East Midlands All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Yelvertoft Wind Farm
Developer / operator
Greencoat UK Wind
Planning authority
West Northamptonshire
Planning reference
DA/2009/0350
Application submitted
15 May 2009
Permission granted
20 July 2010
Construction started
1 June 2012
Began operating
11 July 2013
Capacity in planning record
16 MW
Address
Land Adjacent Glebe Farm, Hillmorton Lane, Yelvertoft (Access Off Rugby Road, Crick), Northamptonshire, Northamptonshire
REPD reference
3978

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.