WIND Β· OPERATIONAL

Swinford

Swinford is a 22 MW onshore wind farm in East Midlands England, operated by Vattenfall. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • East Midlands
  • England
Project stageOperating
  1. PlanningApr 2008 (completed)
  2. ConsentedDec 2009 (completed)
  3. ConstructionDec 2011 (completed)
  4. OperatingNov 2012 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
22 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Vattenfall
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Coordinates
52.4119, -1.1663

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Swinford compares

212th of 488largest wind farms in the UK register
7th of 34in East Midlands
0.07%of listed UK wind farms capacity
β‰ˆ 50 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 22 MW station would generate roughly 50 GWh of electricity in a year, similar to the annual use of about 18,560 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East Midlands All run by Vattenfall

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Swinford Wind Farm
Developer / operator
Nuon UK
Planning authority
Harborough
Planning reference
08/00506/FUL
Application submitted
9 April 2008
Permission granted
30 December 2009
Construction started
1 December 2011
Began operating
21 November 2012
Capacity in planning record
22 MW
Address
Lutterworth Road, Swinford, Lutterworth, Leicestershire. LE17 6BA, Leicestershire
REPD reference
3685

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.