Watford Lodge
Watford Lodge is a 10.3 MW onshore wind farm in East Midlands England, operated by Capital Dynamics UK. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- East Midlands
- England
Key facts
- Installed capacity
- 10.3 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Capital Dynamics UK
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- NN6 7UN
- Coordinates
- 52.3265, -1.1069
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Watford Lodge compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 10.3 MW station would generate roughly 23 GWh of electricity in a year, similar to the annual use of about 8,650 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in East Midlands All run by Capital Dynamics UKNearby generating sites
- Daintree Β· 4 MW onshore wind farm4.0 km
- Winwick Β· 12.3 MW onshore wind farm5.2 km
- Whilton Β· 0.33 MW solar farm5.7 km
- Yelvertoft Β· 16.4 MW onshore wind farm6.1 km
- Swinford Β· 22 MW onshore wind farm10.3 km
- Kelmarsh Β· 12.3 MW onshore wind farm14.0 km
- Streetfield Β· 50 MW solar farm16.2 km
- Low Spinney Β· 8.2 MW onshore wind farm20.2 km
Also operated by Capital Dynamics UK
Capital Dynamics UK operates 25 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- Broadview Energy
- Planning authority
- West Northamptonshire
- Planning reference
- DA/2009/0620
- Application submitted
- 19 August 2008
- Permission granted
- 21 December 2011
- Construction started
- 1 December 2014
- Began operating
- 23 November 2015
- Capacity in planning record
- 12.5 MW
- Address
- runs from Watford to West Hadon Road along norhtern side of railway, Northamptonshire
- REPD reference
- 4424
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.