SOLAR Β· OPERATIONAL

Gaultney

Gaultney is a 21.6 MW solar farm in East Midlands England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East Midlands
  • England

Key facts

Installed capacity
21.6 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
NN14 2SW
Coordinates
52.4476, -0.8070

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Gaultney compares

43rd of 662largest solar farms in the UK register
8th of 95in East Midlands
0.38%of listed UK solar farms capacity
β‰ˆ 19 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 21.6 MW station would generate roughly 19 GWh of electricity in a year, similar to the annual use of about 7,000 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East Midlands All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Gaultney Solar Park
Developer / operator
United Photovoltaics
Planning authority
North Northamptonshire
Planning reference
KET/2014/0391
Application submitted
17 June 2014
Permission granted
5 September 2014
Construction started
1 December 2014
Began operating
31 March 2015
Capacity in planning record
20.5 MW
Address
Gaultney Farm, Pipewell Road, Desborough, Northamptonshire, NN14 2SW
REPD reference
2188

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.