The aluminium smelter's captive coal plant. Lynemouth is a 26 MW wind farm in North East England, operated by Scottish Power. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • North East
  • England
  • Commissioned 1972
  • Closed 2015

Key facts

Installed capacity
26 MW
Status
Operational
Technology
Wind
Operator
Scottish Power
Region
North East
Country
England
Coordinates
55.2016, -1.5396
Commissioned
1972
Closed
2015
Units
3
Unit capacity mw
140
Original purpose
Captive supply for Alcan aluminium smelter

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Lynemouth compares

186th of 488largest wind farms in the UK register
7th of 41in North East
0.09%of listed UK wind farms capacity
β‰ˆ 59 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 26 MW station would generate roughly 59 GWh of electricity in a year, similar to the annual use of about 21,930 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in North East All run by Scottish Power

About Lynemouth

History

Commissioned in 1972 to power the Alcan aluminium smelter next door. One of the few UK coal stations built as a captive industrial supply rather than for the grid. Three 140 MW units. Closed for coal generation at end of 2015 and converted to biomass, reopening in 2018.

The site today

Coal generation ceased December 2015. Converted to biomass and reopened 2018 as Lynemouth Power Ltd. Still operating on wood pellets.

Did you know?

  • Originally built for the Alcan aluminium smelter next door
  • Converted to biomass in 2018
  • Uses wood pellets imported from North America
  • One of the few UK coal stations built for industrial rather than grid supply

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Lynemouth Windfarm (Resubmission)
Developer / operator
Scottish Power Renewables
Planning authority
Northumberland
Planning reference
CM/20060984
Application submitted
20 November 2006
Permission granted
8 January 2009
Construction started
1 July 2010
Began operating
12 April 2012
Capacity in planning record
26 MW
Address
Land adjacent to Rio Tinto Alcan Smelter, Lynemouth (2km north of Ashington), Northumberland
REPD reference
3752

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.