WIND Β· OPERATIONAL

Marr Wind Farm

Marr Wind Farm is a 8.2 MW onshore wind farm in Yorkshire and the Humber, England, operated by The Banks Group. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Yorkshire and the Humber
  • England
Project stageOperating
  1. PlanningDec 2006 (completed)
  2. ConsentedJul 2007 (completed)
  3. ConstructionMar 2011 (completed)
  4. OperatingJan 2012 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
8.2 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
The Banks Group
Region
Yorkshire and the Humber
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
DN5 7AZ
Coordinates
53.5414, -1.2255

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Marr Wind Farm compares

358th of 488largest wind farms in the UK register
25th of 31in Yorkshire and the Humber
0.03%of listed UK wind farms capacity
β‰ˆ 19 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 8.2 MW station would generate roughly 19 GWh of electricity in a year, similar to the annual use of about 6,920 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Yorkshire and the Humber All run by The Banks Group

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Marr Windfarm
Developer / operator
Banks Renewables
Planning authority
Doncaster
Planning reference
07/00445/FULA
Application submitted
20 December 2006
Permission granted
17 July 2007
Construction started
1 March 2011
Began operating
18 January 2012
Capacity in planning record
8 MW
Address
Marr, South Yorkshire, South Yorkshire
REPD reference
3963

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.