SOLAR Β· OPERATIONAL

Misson Park

Misson Park is a 4.99 MW solar farm in East Midlands England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East Midlands
  • England
Project stageOperating
  1. PlanningFeb 2015 (completed)
  2. ConsentedOct 2015 (completed)
  3. ConstructionJan 2016 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.99 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
DN10 6DP
Coordinates
53.4450, -0.9922

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Misson Park compares

351st of 662largest solar farms in the UK register
51st of 95in East Midlands
0.09%of listed UK solar farms capacity
β‰ˆ 4.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.99 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East Midlands All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Misson Solar Farm
Developer / operator
Novus
Planning authority
Bassetlaw
Planning reference
15/00215/FUL
Application submitted
18 February 2015
Permission granted
27 October 2015
Construction started
25 January 2016
Began operating
24 March 2016
Capacity in planning record
5 MW
Address
Bawtry Road, Misson, Nottinghamshire, DN10 6BU
REPD reference
6181

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.