FM1
FM1 is a 79 MW energy-from-waste plant in Yorkshire and the Humber, England, operated by Co-owned by SSE Group and Wheelabrator Technologies Inc. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Bioenergy
- Yorkshire and the Humber
- England
Key facts
- Installed capacity
- 79 MW
- Status
- Operational
- Technology
- Bioenergy
- Operator
- Co-owned by SSE Group and Wheelabrator Technologies Inc
- Region
- Yorkshire and the Humber
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- WF11 8TB
- Coordinates
- 53.7164, -1.2819
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How FM1 compares
Energy-from-waste plants burn residual household and commercial waste that cannot be recycled, using the heat to generate electricity and sometimes heat for nearby buildings.
All energy-from-waste plants Power stations in Yorkshire and the HumberNearby power stations
- FM2 Β· 79 MW energy-from-waste plant0.0 km
- Ferrybridge C Power Station Β· 2,000 MW coal-fired power station0.3 km
- Ash Row Farm Β· 5 MW solar farm9.9 km
- Eggborough Power Station Β· 1,960 MW coal-fired power station10.3 km
- Hook Moor Wind Farm Β· 10 MW onshore wind farm11.7 km
- Askern Β· 4.97 MW solar farm13.4 km
- Primrose Hill Β· 4.35 MW solar farm13.6 km
- Pollington Airfield Β· 5 MW solar farm14.8 km
Also operated by Co-owned by SSE Group and Wheelabrator Technologies Inc
Co-owned by SSE Group and Wheelabrator Technologies Inc operates 2 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Ferrybridge Multifuel 1 (FM1)
- Developer / operator
- Scottish and Southern Energy (SSE)
- Planning authority
- Wakefield
- Planning reference
- 09/02103/OHL
- Application submitted
- 29 October 2009
- Permission granted
- 31 October 2011
- Construction started
- 1 October 2012
- Began operating
- 3 August 2015
- Capacity in planning record
- 68 MW
- Address
- Ferrybridge C Power Station, PO Box 39, Stranglands Lane, Knottingley,, West Yorkshire, WF11 8SQ
- REPD reference
- 116
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.