πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Pierces Farm

Pierces Farm is a 1.74 MW solar farm in South East England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South East
  • England
Project stageOperating
  1. PlanningDec 2013 (completed)
  2. ConsentedMar 2014 (completed)
  3. ConstructionOct 2014 (completed)
  4. OperatingMar 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
1.74 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
South East
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
RG7 1LY
Coordinates
51.4006, -1.0222

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Pierces Farm compares

622nd of 662largest solar farms in the UK register
101st of 105in South East
0.03%of listed UK solar farms capacity
β‰ˆ 1.5 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 1.74 MW station would generate roughly 1.5 GWh of electricity in a year, similar to the annual use of about 560 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South East All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
NextEnergy Capital
Planning authority
West Berkshire
Planning reference
13/03187/COMIND
Application submitted
23 December 2013
Permission granted
19 March 2014
Construction started
16 October 2014
Began operating
15 March 2015
Capacity in planning record
1.7 MW
Address
Land North Of Goring Lane, Grazeley, Reading, Berkshire, Berkshire
REPD reference
1306

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.