πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Hill End Farm

Hill End Farm is a 2.84 MW solar farm in South East England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South East
  • England
Project stageOperating
  1. PlanningJul 2013 (completed)
  2. ConsentedDec 2013 (completed)
  3. Construction (completed)
  4. OperatingMar 2014 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
2.84 MW
Status
Operational
Technology
Solar Β· PV
Operator
Octopus Investments
Region
South East
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
RG26 5HA
Coordinates
51.3118, -1.1114

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Hill End Farm compares

585th of 662largest solar farms in the UK register
95th of 105in South East
0.05%of listed UK solar farms capacity
β‰ˆ 2.5 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 2.84 MW station would generate roughly 2.5 GWh of electricity in a year, similar to the annual use of about 920 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South East All run by Octopus Investments

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Lightsource Renewable Energy
Planning authority
Basingstoke and Deane
Planning reference
13/01007/FUL
Application submitted
12 July 2013
Permission granted
20 December 2013
Began operating
29 March 2014
Capacity in planning record
2.8 MW
Address
Hill End Farm, Aldermaston Road, Salters Heath, Tadley, Hampshire, RG26, Hampshire
REPD reference
2001

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.