Barr Farm
Barr Farm is a 1.89 MW solar farm in West Midlands England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- West Midlands
- England
Key facts
- Installed capacity
- 1.89 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- West Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- WV10 7BN
- Coordinates
- 52.6694, -2.1323
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Barr Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 1.89 MW station would generate roughly 1.7 GWh of electricity in a year, similar to the annual use of about 610 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in West Midlands All run by AnescoNearby generating sites
- Lawn Lane Β· 4.32 MW solar farm3.3 km
- Rodbaston Β· 4 MW onshore wind farm3.8 km
- Albrighton Β· 4.97 MW solar farm7.7 km
- Sheriffhales Β· 5 MW solar farm16.5 km
- Rugeley B Power Station Β· 1,050 MW coal-fired power station17.0 km
- Granville Β· 4.44 MW solar farm19.5 km
- Ironbridge B Power Station Β· 1,000 MW coal-fired power station25.3 km
- Heartlands Β· 100 MW open-cycle gas power station28.1 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- Lark Energy
- Planning authority
- South Staffordshire
- Planning reference
- 14-00406-FUL
- Application submitted
- 4 June 2014
- Permission granted
- 19 August 2014
- Construction started
- 1 November 2014
- Began operating
- 1 April 2015
- Capacity in planning record
- 1.8 MW
- Address
- Barr Farm, Stafford Road, Standeford, South Staffordshire, Staffordshire, WV10 7BN
- REPD reference
- 2178
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026