Home › Grid infrastructure › Connection queue
NESO TEC REGISTER · GREAT BRITAINGrid connection projects in the connection queue on the National Grid (England & Wales) network
Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.
Map
Voltage400 kV275 kV132 kVHVDCNew HVAC
ProjectsPlanningConsentedConstructionBuiltMajor project with its own page
Projects
| Project | Capacity | Stage |
|---|---|---|
| Cottam Solar + storage · Gate Burton Energy Park Limited |
500 MW | Consents Approved |
| Cottam PV & BESS Solar + storage · O&G Solar (SPV 44) Limited |
500 MW | Scoping |
| Creyke Beck Solar + storage · Clean Air Renewables Limited |
500 MW | Scoping |
| Culham Storage Battery storage · Culham Storage Limited |
500 MW | Consents Approved |
| Daines NP BESS Battery storage · Daines Flexpower Limited |
500 MW | Scoping |
| Dove Solar Solar + storage · RWE Renewables UK Solar and Storage Limited |
500 MW | Scoping |
| Dungeness Energy Park Solar + storage · South Kent Energy Park Limited |
500 MW | Scoping |
| Dungeness Energy Park (Dungeness 400kV) Solar + storage · South Kent Energy Park Limited |
500 MW | Scoping |
| Earl Shilton BESS Battery storage · Exagen Normanton Energy Reserve Limited |
500 MW | Scoping |
| East Claydon Storage Battery storage · East Claydon Storage Limited |
500 MW | Scoping |
| Eaton Socon Solar Solar + storage · Brockwell Storage & Solar Limited |
500 MW | Scoping |
| Elstree BESS NP Battery storage · Elstree Flexpower Ltd |
500 MW | Scoping |
| Enderby Solar & BESS Solar + storage · Greentech Projects Holding UK Limited |
500 MW | Scoping |
| Ewerby Solar + storage · Leoda Solar Farm Limited |
500 MW | Scoping |
| Feckenham Solar + storage · Igp Solar 14 Limited |
500 MW | Scoping |
| Feckenham Energy Park Battery storage · Green Energy Mab Ltd |
500 MW | Scoping |
| Green Hydrogen Solar Farm Solar + storage · Green Hydrogen Solar Farm Limited |
500 MW | Scoping |
| Greengage Farm Solar + storage · Renewable Energy Systems Limited |
500 MW | Scoping |
| Grendon Solar & BESS Solar + storage · Green Hill Solar Farm Limited |
500 MW | Scoping |
| Greta III Solar + storage · Tagenergy Development UK Limited |
500 MW | Consents Approved |
| Greta IV (b) Solar + storage · Greta IV Limited |
500 MW | Scoping |
| Greta IV (c) Battery storage · Greta IV Limited |
500 MW | Scoping |
| Greta IV (d) Battery storage · Greta IV Limited |
500 MW | Scoping |
| Grimsby BESS Battery storage · Shama BESS Limited |
500 MW | Scoping |
| High Marnham BESS Battery storage · Jg Pears Grid Connection Limited |
500 MW | Scoping |
| Holdsworth Road Battery storage · Mas 002 Limited |
500 MW | Consents Approved |
| Killingholme Energy Park Solar + storage · Exagen Group Limited |
500 MW | Scoping |
| Kingsnorth BESS NP Battery storage · Noriker Power Ltd |
500 MW | Scoping |
| Kinoulton Solar & BESS Solar + storage · Greentech Invest UK (16) Limited |
500 MW | Scoping |
| Lincolnshire Energy Park Solar + storage · Wind 2 Limited |
500 MW | Scoping |
| Long Buckby Solar/BESS Solar + storage · Greentech Invest UK (17) Limited |
500 MW | Scoping |
| Long Stratton PV & BESS Station Solar + storage · East Pye Solar Limited |
500 MW | Scoping |
| Longfield Solar Solar + storage · Longfield Solar Energy Farm Limited |
500 MW | Scoping |
| Ludgershall - Bicester Solar Farm PVDP Solar + storage · SolarFour Ltd |
500 MW | Scoping |
| Manor Farm Battery storage · Qair Renewables UK Limited |
500 MW | Scoping |
| Medway 3 Power Station Battery storage · Medway Power Limited |
500 MW | Scoping |
| Melksham Solar + storage · Lime Down Solar Park Limited |
500 MW | Awaiting Consents |
| Monk Fryston Solar + storage · Light Valley Solar Limited |
500 MW | Scoping |
| Nant Helen Solar + storage · Solar Securities Limited |
500 MW | Scoping |
| NatPower Connah Quay Green Energy Park Battery storage · Connahs Quay Energy Limited |
500 MW | Scoping |
| Oxfordshire Energy Park Solar + storage · Low Carbon Solar Park 40 Limited |
500 MW | Scoping |
| Partridge Farm BESS Battery storage · Apatura Battery Ltd |
500 MW | Scoping |
| Penrhiwdarren Farm Battery storage · Qair Renewables UK Limited |
500 MW | Scoping |
| Project Number 4 Solar + storage · Greta IV Limited |
500 MW | Scoping |
| Project Number 6 Battery storage · Trent BESS II Limited |
500 MW | Scoping |
| Project Number 8 Battery storage · Trent BESS I Limited |
500 MW | Scoping |
| Rosefield Solar + storage · Rosefield Energyfarm Limited |
500 MW | Awaiting Consents |
| Save Our Planet Solar + storage · Save Our Planet Energy Limited |
500 MW | Scoping |
| Somerset Energy Park Solar + storage · Low Carbon Solar Park 35 Limited |
500 MW | Scoping |
| Spennymoor Greener Grid Park Battery storage · Spennymoor Grid Solutions Limited |
500 MW | Scoping |
Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.