NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown1,329586.0 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1,329 projects · page 8 of 27
ProjectCapacityStageConnection siteFrom
Cottam
Solar + storage · Gate Burton Energy Park Limited
500 MWConsents Approved Cottam 400kV Substation
National Grid (England & Wales)
Jul 2030
Cottam PV & BESS
Solar + storage · O&G Solar (SPV 44) Limited
500 MWScoping Cottam 400kV Substation
National Grid (England & Wales)
Oct 2033
Creyke Beck
Solar + storage · Clean Air Renewables Limited
500 MWScoping Creyke Beck 400kV Substation
National Grid (England & Wales)
May 2033
Culham Storage
Battery storage · Culham Storage Limited
500 MWConsents Approved Culham Jet 400kV Substation
National Grid (England & Wales)
Oct 2029
Daines NP BESS
Battery storage · Daines Flexpower Limited
500 MWScoping Manchester South connection node A 400kv
National Grid (England & Wales)
Oct 2037
Dove Solar
Solar + storage · RWE Renewables UK Solar and Storage Limited
500 MWScoping North Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Dungeness Energy Park
Solar + storage · South Kent Energy Park Limited
500 MWScoping Dungeness 400kV Substation
National Grid (England & Wales)
Oct 2037
Dungeness Energy Park (Dungeness 400kV)
Solar + storage · South Kent Energy Park Limited
500 MWScoping East Kent connection node A 400kV Substation
National Grid (England & Wales)
Oct 2033
Earl Shilton BESS
Battery storage · Exagen Normanton Energy Reserve Limited
500 MWScoping Earl Shilton 275kV
National Grid (England & Wales)
Oct 2029
East Claydon Storage
Battery storage · East Claydon Storage Limited
500 MWScoping East Claydon 400kV Substation
National Grid (England & Wales)
Oct 2026
Eaton Socon Solar
Solar + storage · Brockwell Storage & Solar Limited
500 MWScoping Eaton Socon 400kV Substation
National Grid (England & Wales)
Oct 2028
Elstree BESS NP
Battery storage · Elstree Flexpower Ltd
500 MWScoping Elstree B 275Kv Substation
National Grid (England & Wales)
Oct 2037
Enderby Solar & BESS
Solar + storage · Greentech Projects Holding UK Limited
500 MWScoping Derbyshire Connection Node H 400kV Substation
National Grid (England & Wales)
Oct 2037
Ewerby
Solar + storage · Leoda Solar Farm Limited
500 MWScoping Navenby 400kV Substation
National Grid (England & Wales)
Oct 2035
Feckenham
Solar + storage · Igp Solar 14 Limited
500 MWScoping Feckenham 400kV Substation
National Grid (England & Wales)
Jul 2029
Feckenham Energy Park
Battery storage · Green Energy Mab Ltd
500 MWScoping Feckenham 400kV Substation
National Grid (England & Wales)
Oct 2033
Green Hydrogen Solar Farm
Solar + storage · Green Hydrogen Solar Farm Limited
500 MWScoping Sealand 400kV Substation
National Grid (England & Wales)
Nov 2037
Greengage Farm
Solar + storage · Renewable Energy Systems Limited
500 MWScoping Biggleswade 400kV Substation
National Grid (England & Wales)
Oct 2034
Grendon Solar & BESS
Solar + storage · Green Hill Solar Farm Limited
500 MWScoping Grendon 400kV Substation
National Grid (England & Wales)
Jul 2029
Greta III
Solar + storage · Tagenergy Development UK Limited
500 MWConsents Approved Drakelow 400kV Substation
National Grid (England & Wales)
Oct 2029
Greta IV (b)
Solar + storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Greta IV (c)
Battery storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Greta IV (d)
Battery storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Grimsby BESS
Battery storage · Shama BESS Limited
500 MWScoping Grimsby West 400kV Substation
National Grid (England & Wales)
Apr 2035
High Marnham BESS
Battery storage · Jg Pears Grid Connection Limited
500 MWScoping High Marnham 400kV Substation
National Grid (England & Wales)
Oct 2034
Holdsworth Road
Battery storage · Mas 002 Limited
500 MWConsents Approved Bradford West 275kV Substation
National Grid (England & Wales)
Oct 2036
Killingholme Energy Park
Solar + storage · Exagen Group Limited
500 MWScoping South Humber Connection Node A 400kV
National Grid (England & Wales)
Oct 2035
Kingsnorth BESS NP
Battery storage · Noriker Power Ltd
500 MWScoping Kingsnorth 400kV Substation
National Grid (England & Wales)
Dec 2030
Kinoulton Solar & BESS
Solar + storage · Greentech Invest UK (16) Limited
500 MWScoping Trent Valley North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Lincolnshire Energy Park
Solar + storage · Wind 2 Limited
500 MWScoping South Humber Connection Node A 400kV
National Grid (England & Wales)
Oct 2039
Long Buckby Solar/BESS
Solar + storage · Greentech Invest UK (17) Limited
500 MWScoping Derbyshire Connection Node I 400kV Substation
National Grid (England & Wales)
Oct 2037
Long Stratton PV & BESS Station
Solar + storage · East Pye Solar Limited
500 MWScoping Long Stratton 400kV
National Grid (England & Wales)
Oct 2031
Longfield Solar
Solar + storage · Longfield Solar Energy Farm Limited
500 MWScoping Bulls Lodge 400kV Substation
National Grid (England & Wales)
Oct 2028
Ludgershall - Bicester Solar Farm PVDP
Solar + storage · SolarFour Ltd
500 MWScoping Chiltern Connection Node C 400kV Substation
National Grid (England & Wales)
Nov 2038
Manor Farm
Battery storage · Qair Renewables UK Limited
500 MWScoping East Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Medway 3 Power Station
Battery storage · Medway Power Limited
500 MWScoping Kingsnorth 400kV Substation
National Grid (England & Wales)
Apr 2032
Melksham
Solar + storage · Lime Down Solar Park Limited
500 MWAwaiting Consents Melksham 400kV Substation
National Grid (England & Wales)
Jul 2030
Monk Fryston
Solar + storage · Light Valley Solar Limited
500 MWScoping Monk Fryston 400kV Substation
National Grid (England & Wales)
Dec 2029
Nant Helen
Solar + storage · Solar Securities Limited
500 MWScoping South Wales West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
NatPower Connah Quay Green Energy Park
Battery storage · Connahs Quay Energy Limited
500 MWScoping Cheshire Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Oxfordshire Energy Park
Solar + storage · Low Carbon Solar Park 40 Limited
500 MWScoping Chiltern Connection Node D 400kV
National Grid (England & Wales)
Oct 2037
Partridge Farm BESS
Battery storage · Apatura Battery Ltd
500 MWScoping Sellindge 400kV Substation
National Grid (England & Wales)
Oct 2037
Penrhiwdarren Farm
Battery storage · Qair Renewables UK Limited
500 MWScoping Cilfynydd 400kV Substation
National Grid (England & Wales)
Sep 2037
Project Number 4
Solar + storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Project Number 6
Battery storage · Trent BESS II Limited
500 MWScoping Trent Valley South Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Project Number 8
Battery storage · Trent BESS I Limited
500 MWScoping Trent Valley South Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Rosefield
Solar + storage · Rosefield Energyfarm Limited
500 MWAwaiting Consents East Claydon 400kV Substation
National Grid (England & Wales)
Oct 2031
Save Our Planet
Solar + storage · Save Our Planet Energy Limited
500 MWScoping Sussex and Romney Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Somerset Energy Park
Solar + storage · Low Carbon Solar Park 35 Limited
500 MWScoping Gravity 400kV Substation
National Grid (England & Wales)
Oct 2037
Spennymoor Greener Grid Park
Battery storage · Spennymoor Grid Solutions Limited
500 MWScoping Spennymoor 400kV Substation
National Grid (England & Wales)
Oct 2035
Page 8 of 27

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.