Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown968461.1 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

968 projects · page 18 of 20
ProjectCapacityStageConnection siteFrom
Valley Farm
Battery storage · Starlight Energy UK Limited
100 MWScoping Bishops Wood GSP
National Grid (England & Wales)
Oct 2037
Dollymans Storage
Battery storage · Dollymans Storage Limited
100 MWScoping Rayleigh Main 132kV Substation
National Grid (England & Wales)
Jan 2023
KX Alpha 1 Iron Acton
Battery storage · Kxp Alpha I Limited
99 MWScoping Severn Connection Node A 400kv Substation
National Grid (England & Wales)
Oct 2037
KX Alpha 2 Iron Acton
Battery storage · Kxp Alpha II Limited
99 MWScoping Severn Connection Node A 400kv Substation
National Grid (England & Wales)
Oct 2038
Swansea Greener Grid Park - Connection 1
Battery storage · Swansea Grid Solutions Limited
97 MWScoping Swansea North 400kV Substation
National Grid (England & Wales)
Oct 2028
Erebus
Offshore wind · Blue Gem Wind Limited
95 MWScoping Pembroke 132kV Substation
National Grid (England & Wales)
Jul 2028
Llanwern 3
Solar + storage · Future Energy Llanwern Limited
95 MWScoping South Wales East Connection Node A 275kV Substation
National Grid (England & Wales)
Oct 2037
Llanwern Phase 1
Solar + storage · Future Energy Llanwern Limited
95 MWAwaiting Consents Whitson 275kV Substation
National Grid (England & Wales)
Oct 2028
012 NEP Coventry West
Battery storage · New Energy Partnership Limited
92 MWScoping Berkswell GSP
National Grid (England & Wales)
Oct 2034
Laleham
Battery storage · Juniper Energy Limited
90 MWScoping Laleham 132kV Substation
National Grid (England & Wales)
Oct 2030
Nant Ceiment Energy Park
Onshore wind · Nant Ceiment Energy Park Limited
88 MWScoping Pont Abraham GSP
National Grid (England & Wales)
Sep 2027
Orddu Energy Park
Onshore wind · Orddu Energy Park Limited
86 MWScoping North Wales connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Derwydd Bach Energy Park
Solar · Constantine Wind Energy Limited
85 MWScoping Gwyddelwern 400kV Substation
National Grid (England & Wales)
Oct 2037
Mwdwl Eithin Energy Park
Onshore wind · Moel Chwa Energy Park Limited
81 MWScoping Gwyddelwern 400kV Substation
National Grid (England & Wales)
Jun 2030
Weirs Drove
Battery storage · Care Power (Burwell 1) Limited
80 MWScoping Burwell 132kV Substation
National Grid (England & Wales)
Oct 2028
Foel Fach Wind Farm
Wind + storage · Foel Fach Wind Farm Limited
79 MWScoping North Wales connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Necton Greener Grid Park
Battery storage · Necton Grid Solutions Limited
78 MWAwaiting Consents Necton 400kV Substation
National Grid (England & Wales)
Oct 2032
Sellindge (Tertiary)
Battery storage · Pivoted Power LLP
76 MWAwaiting Consents Sellindge 400kV Substation
National Grid (England & Wales)
Oct 2031
Bryn Gilwern Energy Park
Onshore wind · Bryn Gilwern Energy Park Limited
75 MWScoping Pont Abraham GSP
National Grid (England & Wales)
Oct 2026
Calon y Gwynt
Solar + storage · Wind 2 Project 3 Limited
72 MWScoping Mid Wales Connection Node A
National Grid (England & Wales)
Oct 2037
Don Cossack
Battery storage · Don Cossack Ltd
70 MWAwaiting Consents Tynemouth 275kV Substation
National Grid (England & Wales)
Jun 2034
Port of Mostyn
Other · Mostyn Seapower Limited
70 MWScoping Connah's Quay 400kV Substation
National Grid (England & Wales)
Dec 2030
Gaerwen Wind Farm
Onshore wind · RWE Renewables UK Onshore Wind Limited
67 MWAwaiting Consents Gwyddelwern 400kV Substation
National Grid (England & Wales)
Jun 2027
Rochester Renewable Project
Solar + storage · Vattenfall Wind Power Ltd
60 MWScoping Kingsnorth 132kV Substation
National Grid (England & Wales)
Sep 2028
Aberthaw (Tertiary)
Solar + storage · Aberthaw Green Limited
57 MWScoping Aberthaw 275kV Substation
National Grid (England & Wales)
Oct 2029
Arkwright
Battery storage · Arlington (Group Services) Limited
57 MWScoping Chesterfield 400kV Substation (Not yet constructed)
National Grid (England & Wales)
Oct 2034
Bicker Fen 2 Solar
Solar + storage · Agr Solar 3 Limited
57 MWScoping Bicker Fen 400kV Substation
National Grid (England & Wales)
Apr 2033
Biggleswade BESS
Battery storage · Central Bedfordshire Council
57 MWScoping Biggleswade 400kV Substation
National Grid (England & Wales)
Sep 2029
Bolney (tertiary)
Solar + storage · Bolney Green Limited
57 MWScoping Bolney 400kV Substation
National Grid (England & Wales)
May 2028
Bramford 2 GEC (Ethos Green)
Solar + storage · Bramford 2 Green Energy Centre Ltd
57 MWAwaiting Consents Bramford 400kV Substation
National Grid (England & Wales)
Jul 2032
Bridgwater (tertiary)
Solar + storage · Enso Green Holdings H Limited
57 MWScoping Bridgwater 400/132kV Substation
National Grid (England & Wales)
Aug 2028
Bridgwater 2 (tertiary) - New Conn
Solar + storage · Bridgwater Green Limited
57 MWScoping Bridgewater 400kV Substation
National Grid (England & Wales)
Aug 2029
Burwell (Tertiary)
Battery storage · Pivoted Power LLP
57 MWAwaiting Consents Burwell Main 400kV Substation
National Grid (England & Wales)
Jun 2029
Canterbury Tertiary
Solar + storage · Enso Green Holdings L Limited
57 MWAwaiting Consents Canterbury North 400kV Substation
National Grid (England & Wales)
Oct 2031
Capenhurst Tertiary
Solar + storage · Enso Green Holdings Q Limited
57 MWScoping Capenhurst 400kV Substation
National Grid (England & Wales)
Oct 2027
Carrington
Battery storage · Pivoted Power LLP
57 MWAwaiting Consents Carrington 275kV Substation
National Grid (England & Wales)
Oct 2028
Cowley (Tertiary)
Solar + storage · Cowley Baldon Green Limited
57 MWScoping Cowley 400kV Substation
National Grid (England & Wales)
Nov 2025
ER BUR Energy
Solar + storage · Er Project Development Co Limited
57 MWScoping Burwell South 400kV Substation
National Grid (England & Wales)
Oct 2033
ER HTP Energy
Solar + storage · Er Project Development Co Limited
57 MWScoping Hawthorn Pit 400kV Substation
National Grid (England & Wales)
Jun 2034
ER LBR Energy
Solar + storage · Er Project Development Co Limited
57 MWScoping Littlebrook 400kV Substation
National Grid (England & Wales)
Oct 2029
Exeter (Tertiary)
Solar + storage · Pivoted Power LLP
57 MWScoping Exeter 400kV Substation
National Grid (England & Wales)
Dec 2036
Exeter Main Tertiary
Gas · Exeter Main Battery Limited
57 MWScoping Exeter 400kV Substation
National Grid (England & Wales)
May 2024
Fleet Solar PV
Solar · Fleet Solar Limited
57 MWAwaiting Consents Fleet 400kV Substation
National Grid (England & Wales)
Aug 2028
Kirkby (Tertiary)
Solar + storage · Pivoted Power LLP
57 MWScoping Kirkby 275/33kV Substation
National Grid (England & Wales)
Aug 2027
Landulph
Solar + storage · Pivoted Power LLP
57 MWScoping Landulph 400kV Substation
National Grid (England & Wales)
Oct 2028
Lister Drive Shaw
Battery storage · Carnegie (BES) Ltd
57 MWScoping Lister Drive 275kV Substation
National Grid (England & Wales)
Sep 2026
Little Horsted
Solar + storage · Lightsource Renewable UK Development Limited
57 MWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Lovedean (Tertiary)
Solar + storage · Lovedean Green Limited
57 MWScoping Lovedean 400kV Substation
National Grid (England & Wales)
Oct 2029
Melksham (Tertiary)
Solar + storage · Melksham Calne Green Limited
57 MWScoping Melksham 400kV Substation
National Grid (England & Wales)
Jun 2026
Norton
Battery storage · Baywa R.e. UK Limited
57 MWAwaiting Consents Norton 275kV Substation
National Grid (England & Wales)
Jun 2029
Page 18 of 20

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.