Bridgwater (tertiary) is a 57 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Bridgwater 400/132kV Substation, with capacity due from August 2028. The connection agreement is held by Enso Green Holdings H Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-000375
Customer
Enso Green Holdings H Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
57 MW
Change in this agreement
+57 MW
Capacity effective from
31 August 2028
Connection site
Bridgwater 400/132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.

Projects connecting near Bridgwater · Grid map

Other projects at Bridgwater 400/132kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem