Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · NGETMwdwl Eithin Energy Park
Mwdwl Eithin Energy Park is a 81 MW onshore wind project in planning, connecting to the National Grid (England & Wales) network at Gwyddelwern 400kV Substation, with capacity due from June 2030. The connection agreement is held by Moel Chwa Energy Park Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Jun 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001511
- Customer
- Moel Chwa Energy Park Limited
- Technology
- Wind Onshore
- Total capacity
- 81 MW
- Change in this agreement
- +81 MW
- Capacity effective from
- 30 June 2030
- Connection site
- Gwyddelwern 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.
Other projects at Gwyddelwern 400kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem