Grid connection projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown1,590616.3 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1,590 projects · page 12 of 32
ProjectCapacityStageConnection siteFrom
Tyler Hill Bicker Fen
Battery storage · FRV Powertek Limited
400 MWScoping Coddington 400kV Substation
National Grid (England & Wales)
May 2035
Willington Green Energy Centre
Solar + storage · Willington Ng Limited
400 MWScoping Willington 400kV Substation
National Grid (England & Wales)
Oct 2028
Woodbridge - Noventum
Battery storage · Noventum Power Solar 16 Limited
400 MWScoping South Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Wymondley
Solar + storage · Enso Green Holdings Limited
400 MWScoping Wymondley 400kV Substation
National Grid (England & Wales)
Oct 2032
Noventum - Budby
Solar + storage · Noventum Power Solar 15 Limited
380 MWScoping Trent Valley South Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2035
Noventum- Bridgwater
Battery storage · Noventum Power Solar 13 Limited
380 MWScoping Woolavington 400kV Substation
National Grid (England & Wales)
Oct 2037
Mon Solar Farm
Solar + storage · Lightsource Spv 204 Limited
360 MWScoping Wylfa South 400kV Substation
National Grid (England & Wales)
Oct 2037
Whitelee
Onshore wind · Scottish Power Renewables (UK) Limited
355 MWScoping Whitelee 275/33kV
SP Transmission (south Scotland)
May 2031
Bernicia Energy Park
Solar + storage · Baywa R.e. UK Limited
350 MWScoping Stella West 400kV Substation
National Grid (England & Wales)
Oct 2035
Bulls Lodge Farm 2
Solar + storage · 548 UK Investment Holdings Limited
350 MWScoping Braintree 400kV Substation
National Grid (England & Wales)
Mar 2033
Caegarw Farm
Solar + storage · Downing Renewable Developments LLP
350 MWScoping Margam B 400kV Substation
National Grid (England & Wales)
May 2037
Denny BESS
Battery storage · Igp Energy Storage 3 Limited
350 MWScoping Denny North
SP Transmission (south Scotland)
Oct 2030
Marston Farm 2
Solar + storage · 548 UK Investment Holdings Limited
350 MWScoping Marston Vale 400kV Substation
National Grid (England & Wales)
Oct 2032
Patford Bridge Farm 2
Solar + storage · 548 UK Investment Holdings Limited
350 MWScoping New Patford Bridge 400kV Substation
National Grid (England & Wales)
Oct 2033
Project Invicta
Solar + storage · Project Invicta Limited
350 MWScoping East Kent Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2036
Sedgeby Solar Farm
Solar + storage · Sedgeby Solar Limited
350 MWAwaiting Consents Thormanby 400kV Substation
National Grid (England & Wales)
Oct 2033
Stack Hill Solar and Storage
Solar + storage · RWE Renewables UK Solar and Storage Limited
350 MWScoping Trent Valley South Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Westfield BESS
Battery storage · Brockwell Energy Limited
350 MWScoping Westfield 400kV Substation
SP Transmission (south Scotland)
Oct 2031
Whitson BESS NP
Battery storage · Equinor New Energy Limited
350 MWScoping South Wales East Node A 275kV Substation
National Grid (England & Wales)
Oct 2037
Shotwick BESS
Battery storage · Shotwick Land Limited
350 MWScoping Merseyside Connection Node A 400Kv Substation
National Grid (England & Wales)
Oct 2037
Cilfynydd BESS
Battery storage · Cilfynydd BESS Limited
350 MWScoping Cilfynydd 400kV Substation
National Grid (England & Wales)
Oct 2037
SAE Usk 1
Battery storage · Afon Wysg Energy Limited
349 MWScoping South Wales East Node A 275kV Substation
National Grid (England & Wales)
Oct 2037
ESB Harker BESS
Battery storage · Esb (Harker) Ltd
342 MWScoping Harker 400kV Substation
National Grid (England & Wales)
Oct 2039
Blacklaw
Wind + storage · Scottish Power Renewables (UK) Limited
340 MWScoping Blacklaw 132/33kV
SP Transmission (south Scotland)
Oct 2032
Melton Mowbray Solar
Solar + storage · Cubico UK Development Limited
340 MWScoping West Anglia Connection Node I 400kV substation
National Grid (England & Wales)
Oct 2037
Pittlesheugh Farm
Battery storage · Pittlesheugh Farm BESS Limited
340 MWScoping Eccles 400/132kV
SP Transmission (south Scotland)
Oct 2030
Tween Bridge Solar Park
Solar + storage · RWE Renewables UK Solar and Storage Limited
340 MWScoping Trent Valley North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2029
High Mathernock Battery Storage
Battery storage · Harmony HM Limited
334 MWScoping High Mathernock 132Kv Substation
SP Transmission (south Scotland)
Oct 2029
Park Farm Hybrid Solar and BESS
Solar + storage · Voltalia UK Ltd
332 MWScoping Derbyshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Arecleoch
Onshore wind · Scottish Power Renewables (UK) Limited
330 MWScoping Arecleoch 132/33kV
SP Transmission (south Scotland)
Jun 2032
Zenobe Butler's Wood BESS
Battery storage · Zenobe Energy Limited
330 MWScoping Butlers Wood 400kV Substation
National Grid (England & Wales)
Oct 2034
Creyke Beck Solar Farm
Solar · RWE Renewables UK Solar and Storage Limited
320 MWScoping Creyke Beck GSP
National Grid (England & Wales)
May 2033
Hurst BESS
Battery storage · Luminous Energy Group Limited
320 MWScoping North Kent Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2037
Calderdale Wind Farm 312MW
Onshore wind · Calderdale Wind Farm Ltd
312 MWScoping Leeds North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2035
AGS Calderside Battery Energy Storage System
Battery storage · Advance Grid Solutions Limited
300 MWScoping Ags Calderside 275Kv Substation
SP Transmission (south Scotland)
Oct 2029
Aitkenhead Farm BESS
Battery storage · Aitkenhead Storage Facility Limited
300 MWScoping Clydesmill 275/33kV
SP Transmission (south Scotland)
Apr 2033
Alcemi Midmill BESS
Battery storage · Alcemi Storage Developments 2 Limited
300 MWScoping Kintore 275kV
SSEN Transmission (north Scotland)
Dec 2029
Boom Power Seaton Hill Generation HUB
Battery storage · Seatonhill Storage Facility Limited
300 MWScoping Cockenzie 400/275kV
SP Transmission (south Scotland)
Oct 2033
Castlemilk 1
Solar · Queequeg Renewables Ltd
300 MWScoping Castlemilk 400kV Substation
SP Transmission (south Scotland)
Oct 2036
Chickerell
Solar + storage · Enso Green Holdings X Limited
300 MWAwaiting Consents Chickerell 400kV Substation
National Grid (England & Wales)
Oct 2037
Coddington BESS
Battery storage · Shaw-Energi Ltd
300 MWScoping Trent Valley South Connection Node A 400kV
National Grid (England & Wales)
Oct 2034
Coylton Farm
Battery storage · New Energy Partnership Limited
300 MWAwaiting Consents Coylton 275/33kV Substation
SP Transmission (south Scotland)
Oct 2037
Craig Moss Farm
Battery storage · Qair Renewables UK Limited
300 MWScoping Craig Moss Farm 132kV Substation
SP Transmission (south Scotland)
Oct 2036
Cranwell Solar & BESS Farm
Solar + storage · Trio Power Limited
300 MWScoping Trent Valley South Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Crossgatehall BESS
Battery storage · De 001 Limited
300 MWScoping Smeaton 400/275kV
SP Transmission (south Scotland)
Oct 2033
Didcot Energy Park
Battery storage · Brockwell Storage & Solar Limited
300 MWAwaiting Consents Didcot 400kV Substation
National Grid (England & Wales)
Oct 2027
Dragon Green BESS
Battery storage · Shaw-Energi Ltd
300 MWScoping Sussex and Romney Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Elmya Bathgate BESS
Battery storage · Rpc Elmya Carnation Bathgate Limited
300 MWScoping Armadale 400kv Substation
SP Transmission (south Scotland)
Oct 2031
Elmya Grange Road
Solar + storage · Elmya Rpc UK Grange Road Limited
300 MWAwaiting Consents Elmya Grange 400kV
National Grid (England & Wales)
Oct 2031
Elmya Melbourne BESS
Battery storage · Elmya Rpc UK Melbourne Limited
300 MWScoping Thornton 400kV Substation
National Grid (England & Wales)
Oct 2039
Page 12 of 32

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.