Grid infrastructure β€Ί Connection queue β€Ί Solar + storage

SOLAR + STORAGE Β· NGET

Wymondley

Wymondley is a 400 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Wymondley 400kV Substation, with capacity due from October 2032. The connection agreement is held by Enso Green Holdings Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2032 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002187
Customer
Enso Green Holdings Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
400 MW
Change in this agreement
+400 MW
Capacity effective from
31 October 2032
Connection site
Wymondley 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Wymondley Β· Grid map

Other projects at Wymondley 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem