🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

Sedgeby Solar Farm

Sedgeby Solar Farm is a 350 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Thormanby 400kV Substation, with capacity due from October 2033. The connection agreement is held by Sedgeby Solar Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002123
Customer
Sedgeby Solar Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
350 MW
Change in this agreement
+350 MW
Capacity effective from
28 October 2033
Connection site
Thormanby 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Awaiting Consents
Connections reform gate
Gate 1

Connection site

The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.

Projects connecting near Thormanby · Grid map

Other projects at Thormanby 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem