ONSHORE WIND Β· MISO

Onshore wind project G432, Ford County

Onshore wind project G432, Ford County is a 65.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Ford County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2004 (completed)
  2. Withdrawn / abandonedNov 2011 (project stopped here)
  3. ConsentedNov 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G432
Grid region
MISO (Midcontinent)
Connection point (POI)
Gibson City
Location
Ford County, Illinois
Technology
Wind: 65.0 MW
Total requested
65.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
17 June 2004
Agreement signed
16 November 2011
Proposed online date
December 2005
Withdrawn
November 2011

Location

Marker shows the centre of Ford County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Ford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem