Solar project 295, Alachua County

Solar project 295, Alachua County is a 74.5 MW solar request withdrawn in the Southeast interconnection queue, in Alachua County, Florida, connecting to Florida Power & Light.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
295
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Bradford-Putnam 115kV
Location
Alachua County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Withdrawn
Entered queue
27 June 2017
Proposed online date
December 2029

Location

Marker shows the centre of Alachua County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Alachua County