United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR Β· WEST

Solar project 1123, Box Elder County

Solar project 1123, Box Elder County is a 3.0 MW solar request withdrawn in the West interconnection queue, in Box Elder County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1123
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Circuit SNO12 out of Snowville substation
Location
Box Elder County, Utah
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
Request moved to transition cluster
Queue status
Withdrawn
Entered queue
29 March 2019
Proposed online date
December 2021

Location

Marker shows the centre of Box Elder County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Box Elder County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem