🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Massachusetts

GAS · ISO-NE

Gas Turbine Capacity Increase( #178)

Gas Turbine Capacity Increase( #178) is a 69.0 MW gas request withdrawn in the ISO-NE interconnection queue, in Plymouth County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2006 (completed)
  2. Withdrawn / abandonedFeb 2007 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
188
Grid region
ISO-NE (New England)
Connection point (POI)
115 kV F19 and/or E20 lines
Location
Plymouth County, Massachusetts
Technology
Gas: 69.0 MW · Oil
Total requested
69.0 MW
Service type
Other
Queue status
Withdrawn
Entered queue
7 December 2006
Proposed online date
June 2010
Withdrawn
February 2007

Location

Marker shows the centre of Plymouth County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Plymouth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem