United States › Grid › Interconnection queues › Texas
OTHER · ERCOTWebb County Renewables Storage
Webb County Renewables Storage is a 203 MW other request withdrawn in the ERCOT interconnection queue, in Webb County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2022 (completed)
- Withdrawn / abandonedMar 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0311
- Grid region
- ERCOT (Texas)
- Developer
- Webb County Renewables, LLC
- Connection point (POI)
- 161105 Bordas 345kV
- Location
- Webb County, Texas
- Technology
- Other: 203 MW
- Total requested
- 203 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 24 July 2022
- Proposed online date
- June 2024
- Withdrawn
- March 2024
Location
Marker shows the centre of Webb County; the queue data does not give exact sites.
Other requests in Webb County
- SieteOnshore wind · 493 MW · agreement signed
- Cuchillas SolarSolar + storage · 306 MW · agreement signed
- Corazon Solar Phase IISolar + storage · 204 MW · agreement signed
- Corvus SolarSolar · 202 MW · agreement signed
- Seven Flags BESSBattery storage · 103 MW · agreement signed
- Cedro Hill Wind RepowerOnshore wind · 9.9 MW · agreement signed
- Torrecillas BESSBattery storage · 9.9 MW · agreement signed
- Outpost StorageSolar + storage · 508 MW · in study
- Siete WindOnshore wind · 493 MW · in study
- Cuchillas BESSSolar + storage · 307 MW · in study
- Cenizo SolarSolar · 301 MW · in study
- Bendito WindOnshore wind · 300 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem