United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Solar interconnection queue in the USA (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown191,524 MW
Active in queue1,524 MW19 requests
Agreement signed306 MW6 requests
Withdrawn38315.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

19 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Morada Del Sol Solar
Solar Β· First Solar
245 MWPaused / redesign Upton, TXERCOT Mar 2015target 2020
Solar project Q230, Navajo County
Solar
200 MWUnder construction Navajo, AZWest Sep 2015target 2021
Whatley Solar
Solar Β· Invenergy
150 MWPaused / redesign Andrews, TXERCOT May 2015target 2020
Wake Solar
Solar Β· Invenergy
150 MWPaused / redesign Crosby, TXERCOT Jul 2015target 2021
Solar project J483, Liberty County
Solar
100 MWAgreement signed Liberty, TXMISO Sep 20152024
Solar project J524, Webster County
Solar
100 MWAgreement signed Webster, IAMISO Nov 20152022
Mohawk Solar
Solar Β· Mohawk Solar LLC
90.5 MWIn study Montgomery, NYNYISO Apr 2015target 2027
Solar project G0517, Morrow County
Solar
76.0 MWIn study Morrow, ORWest Nov 2015target 2018
Owego Solar
Solar Β· Hecate Energy
74.0 MWPaused / redesign Pecos, TXERCOT Apr 2015target 2020
Solar project BHCT G19, Pueblo County
Solar
60.0 MWIn study Pueblo, COWest Apr 2015target 2019
Chatee Solar
Solar Β· Hecate Energy
57.0 MWPaused / redesign Pecos, TXERCOT Apr 2015target 2020
Solar project J504, Linn County
Solar
50.0 MWAgreement signed Linn, IAMISO Nov 20152024
Solar project J523, Mower County
Solar
50.0 MWAgreement signed Mower, MNMISO Nov 20152024
Solar project 39, Orangeburg County
Solar
42.0 MWUnder construction Orangeburg, SCSoutheast Jun 2015target 2016
Hecate Solar
Solar Β· Hecate Energy
33.0 MWPaused / redesign Brewster, TXERCOT Mar 2015target 2020
Solar project G0516, Sherman County
Solar
20.0 MWIn study Sherman, ORWest Oct 2015target 2016
Solar project G0513, Morrow County
Solar
20.0 MWIn study Morrow, ORWest Sep 2015target 2016
Cedar Lane Solar
Solar
4.0 MWAgreement signed Queen Anne's, MDPJM Oct 2015target 2026
Solar project 11
Solar
2.0 MWAgreement signed FLSoutheast Aug 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)