πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Washington (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown223,657 MW
Active in queue3,657 MW22 requests
Agreement signed430 MW5 requests
Withdrawn494,360 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

22 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project G0608, Klickitat County
Battery storage
1,200 MWIn study Klickitat, WAWest Dec 2018target 2027
Solar project G0589, Klickitat County
Solar
381 MWIn study Klickitat, WAWest May 2018target 2023
Onshore wind project G0585, Klickitat County
Onshore wind
313 MWIn study Klickitat, WAWest Mar 2018target 2021
Solar + storage project G0598, Klickitat County
Solar + storage
223 MWIn study Klickitat, WAWest Aug 2018target 2021
Battery storage project 60, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Aug 2018target 2028
Solar project G0602, Grant County
Solar
170 MWIn study Grant, WAWest Oct 2018target 2022
Solar + storage project 60, Asotin County
Solar + storage
150 MWPaused / redesign Asotin, WAWest Jun 2018target 2025
Solar + storage project G0596, Yakima County
Solar + storage
112 MWIn study Yakima, WAWest Jul 2018target 2021
Solar project 55, Douglas County
Solar
101 MWPaused / redesign Douglas, WAWest Jan 2018target 2030
Solar project 56, Douglas County
Solar
101 MWPaused / redesign Douglas, WAWest Jan 2018target 2030
Solar project 73, Adams County
Solar
100 MWIn study Adams, WAWest Oct 2018target 2020
Solar project G0586, Klickitat County
Solar
100 MWIn study Klickitat, WAWest Apr 2018target 2022
Solar project 81, Adams County
Solar
94.0 MWIn study Adams, WAWest Dec 2018target 2020
Solar + storage project 1008, Yakima County
Solar + storage Β· Black Rock Solar, LLC
94.0 MWAgreement signed Yakima, WAWest Mar 2018target 2023
Solar + storage project TCS-03, Adams County
Solar + storage
80.0 MWPaused / redesign Adams, WAWest Aug 2018
Solar project 67, Adams County
Solar
80.0 MWIn study Adams, WAWest Aug 2018target 2023
Other project 66, Stevens County
Other
71.0 MWAgreement signed Stevens, WAWest Jul 2018target 2026
Solar + storage project 59, Adams County
Solar + storage
60.0 MWAgreement signed Adams, WAWest May 2018
Solar + storage project 80, Spokane County
Solar + storage
19.0 MWIn study Spokane, WAWest Dec 2018target 2025
Solar project TCS-14, Yakima County
Solar Β· OneEnergy Development, LLC
5.0 MWAgreement signed Yakima, WAWest Oct 2018target 2027
Battery storage project 70, Spokane County
Battery storage
2.5 MWIn study Spokane, WAWest Aug 2018target 2019
Solar project 71, Lincoln County
Solar
1.0 MWIn study Lincoln, WAWest Oct 2018target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)