United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Utah (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown385,142 MW
Active in queue420 MW3 requests
Agreement signed75.0 MW1 requests
Withdrawn385,142 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

38 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 986, Beaver County
Solar
600 MWWithdrawn / abandoned Beaver, UTWest Dec 2017target 2020
Solar + storage project 976, Utah County
Solar + storage
525 MWWithdrawn / abandoned Utah, UTWest Nov 2017target 2020
Solar + storage project 978, Box Elder County
Solar + storage
525 MWWithdrawn / abandoned Box Elder, UTWest Nov 2017target 2020
Solar + storage project 982, Utah County
Solar + storage
300 MWWithdrawn / abandoned Utah, UTWest Nov 2017target 2020
Solar + storage project 985, Utah County
Solar + storage
300 MWWithdrawn / abandoned Utah, UTWest Nov 2017target 2020
Solar project 997, Iron County
Solar
300 MWWithdrawn / abandoned Iron, UTWest Dec 2017target 2020
Solar + storage project TCS-05, Juab County
Solar + storage
202 MWWithdrawn / abandoned Juab, UTWest Jun 2017target 2023
Solar + storage project 898, Juab County
Solar + storage
202 MWWithdrawn / abandoned Juab, UTWest Jun 2017target 2020
Solar project 980, Box Elder County
Solar
200 MWWithdrawn / abandoned Box Elder, UTWest Nov 2017target 2020
Solar project 851, Juab County
Solar
200 MWWithdrawn / abandoned Juab, UTWest Feb 2017target 2020
Solar project 854, Kane County
Solar
190 MWWithdrawn / abandoned Kane, UTWest Mar 2017target 2020
Solar + storage project 979, Utah County
Solar + storage
160 MWWithdrawn / abandoned Utah, UTWest Nov 2017target 2021
Solar project 975, Juab County
Solar
101 MWWithdrawn / abandoned Juab, UTWest Nov 2017target 2020
Solar project TCS-08, Juab County
Solar
101 MWWithdrawn / abandoned Juab, UTWest Nov 2017target 2023
Solar project 981, Box Elder County
Solar
100 MWWithdrawn / abandoned Box Elder, UTWest Nov 2017target 2020
Solar project 977, Box Elder County
Solar
100 MWWithdrawn / abandoned Box Elder, UTWest Nov 2017target 2020
Solar + storage project 871, Juab County
Solar + storage
100 MWWithdrawn / abandoned Juab, UTWest May 2017target 2020
Onshore wind project 868, Rich County
Onshore wind
80.0 MWWithdrawn / abandoned Rich, UTWest Apr 2017target 2019
Onshore wind project 867, Carbon County
Onshore wind
80.0 MWWithdrawn / abandoned Carbon, UTWest Apr 2017target 2019
Solar project 996, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Dec 2017target 2020
Solar + storage project 865, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2020
Solar + storage project TCS-02, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2023
Solar + storage project 864, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2020
Solar + storage project TCS-03, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2023
Solar project 909, Tooele County
Solar
75.0 MWWithdrawn / abandoned Tooele, UTWest Jul 2017target 2018
Solar project 993, Weber County
Solar
74.9 MWWithdrawn / abandoned Weber, UTWest Dec 2017target 2020
Solar project 941, Weber County
Solar
45.0 MWWithdrawn / abandoned Weber, UTWest Sep 2017target 2019
Solar project 991, Tooele County
Solar
45.0 MWWithdrawn / abandoned Tooele, UTWest Dec 2017target 2019
Solar project 938, Beaver County
Solar
40.0 MWWithdrawn / abandoned Beaver, UTWest Aug 2017target 2018
Solar project 881, Tooele County
Solar
35.0 MWWithdrawn / abandoned Tooele, UTWest May 2017target 2018
Solar project TCS-07, Juab County
Solar
20.0 MWWithdrawn / abandoned Juab, UTWest Oct 2017target 2022
Solar project 966, Juab County
Solar
20.0 MWWithdrawn / abandoned Juab, UTWest Oct 2017target 2018
Solar project 990, Tooele County
Solar
10.0 MWWithdrawn / abandoned Tooele, UTWest Dec 2017target 2019
Solar project 880, Tooele County
Solar
10.0 MWWithdrawn / abandoned Tooele, UTWest May 2017target 2018
Solar project 989, Tooele County
Solar
10.0 MWWithdrawn / abandoned Tooele, UTWest Dec 2017target 2019
Solar project 955, Iron County
Solar
2.0 MWWithdrawn / abandoned Iron, UTWest Oct 2017target 2018
Hydro project 908, Davis County
Hydro
0.2 MWWithdrawn / abandoned Davis, UTWest Jul 2017target 2018
Battery storage project 965, Davis County
Battery storage
0.0 MWWithdrawn / abandoned Davis, UTWest Oct 2017target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)