United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR + STORAGE Β· WEST

Solar + storage project TCS-05, Juab County

Solar + storage project TCS-05, Juab County is a 202 MW solar + storage request withdrawn in the West interconnection queue, in Juab County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
TCS-05
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Clover substation
Location
Juab County, Utah
Technology
Solar: 202 MW Β· Battery
Total requested
202 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
23 June 2017
Proposed online date
December 2023

Location

Marker shows the centre of Juab County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Juab County