πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR + STORAGE Β· WEST

Solar + storage project 898, Juab County

Solar + storage project 898, Juab County is a 202 MW solar + storage request withdrawn in the West interconnection queue, in Juab County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
898
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Clover substation
Location
Juab County, Utah
Technology
Solar: 202 MW Β· Battery
Total requested
202 MW
Service type
NRIS and ERIS
Study phase
Request moved to transition cluster
Queue status
Withdrawn
Entered queue
23 June 2017
Proposed online date
December 2020

Location

Marker shows the centre of Juab County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Juab County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem