United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Texas (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown102,118 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn102,118 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
EPE Gen - Caliente
Gas
348 MWWithdrawn / abandoned El Paso, TXWest Feb 2011target 2015
EPE Gen - Megellan
Gas
348 MWWithdrawn / abandoned El Paso, TXWest Jan 2011target 2015
Wildrose Wind
Onshore wind Β· S Power
303 MWWithdrawn / abandoned Swisher, TXERCOT Apr 2011target 2021
Onshore wind project GEN-2011-021, Hansford County
Onshore wind
299 MWWithdrawn / abandoned Hansford, TXSPP Mar 2011target 2012
Onshore wind project GEN-2011-036, Swisher County
Onshore wind
270 MWWithdrawn / abandoned Swisher, TXSPP Jul 2011target 2014
Onshore wind project GEN-2011-058, Lynn County
Onshore wind
200 MWWithdrawn / abandoned Lynn, TXSPP Sep 2011target 2012
Gas project GEN-2011-031, Ector County
Gas
196 MWWithdrawn / abandoned Ector, TXSPP Mar 2011target 2014
Onshore wind project GEN-2011-012, Sherman County
Onshore wind
105 MWWithdrawn / abandoned Sherman, TXSPP Mar 2011target 2012
Onshore wind project GEN-2011-034, Hall County
Onshore wind
31.0 MWWithdrawn / abandoned Hall, TXSPP Jun 2011target 2013
Onshore wind project GEN-2011-026, Crosby County
Onshore wind
19.7 MWWithdrawn / abandoned Crosby, TXSPP Mar 2011target 2011

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)