United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Texas (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown92,453 MW
Active in queue150 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn92,453 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2010-060, Ector County
Gas
992 MWWithdrawn / abandoned Ector, TXSPP Dec 2010target 2014
Gas project GEN-2010-059, Ector County
Gas
516 MWWithdrawn / abandoned Ector, TXSPP Dec 2010target 2013
Onshore wind project GEN-2010-034, Crosby County
Onshore wind
261 MWWithdrawn / abandoned Crosby, TXSPP Jun 2010target 2012
Onshore wind project GEN-2010-033, Hale County
Onshore wind
230 MWWithdrawn / abandoned Hale, TXSPP Jun 2010target 2014
Onshore wind project GEN-2010-032, Hale County
Onshore wind
216 MWWithdrawn / abandoned Hale, TXSPP Jun 2010target 2014
Granite Mountain Wind Power (Duke Energy Generation Services)
Onshore wind
101 MWWithdrawn / abandoned Hudspeth, TXWest Aug 2010target 2012
Onshore wind project GEN-2010-007, Hutchinson County
Onshore wind
73.8 MWWithdrawn / abandoned Hutchinson, TXSPP Mar 2010target 2011
Gas project GEN-2010-046, Hale County
Gas
56.0 MWWithdrawn / abandoned Hale, TXSPP Sep 20102016
HOVEY (Barilla Solar 1B)
Solar Β· First Solar
7.4 MWWithdrawn / abandoned Pecos, TXERCOT Nov 2010target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)