ONSHORE WIND Β· SPP

Onshore wind project GEN-2010-032, Hale County

Onshore wind project GEN-2010-032, Hale County is a 216 MW onshore wind request withdrawn in the SPP interconnection queue, in Hale County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2010 (completed)
  2. Withdrawn / abandonedOct 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2010-032
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
TUCO 345kV
Location
Hale County, Texas
Technology
Wind: 216 MW
Total requested
216 MW
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
25 June 2010
Proposed online date
January 2014
Withdrawn
October 2010

Location

Marker shows the centre of Hale County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Hale County