United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

GAS Β· SPP

Gas project GEN-2010-060, Ector County

Gas project GEN-2010-060, Ector County is a 992 MW gas request withdrawn in the SPP interconnection queue, in Ector County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2010 (completed)
  2. Withdrawn / abandonedApr 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2010-060
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Midland 345kV
Location
Ector County, Texas
Technology
Gas: 992 MW
Total requested
992 MW
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 December 2010
Proposed online date
June 2014
Withdrawn
April 2012

Location

Marker shows the centre of Ector County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Ector County