United States βΊ Grid βΊ Interconnection queues βΊ Texas
GAS Β· SPPGas project GEN-2010-059, Ector County
Gas project GEN-2010-059, Ector County is a 516 MW gas request withdrawn in the SPP interconnection queue, in Ector County, Texas, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2010 (completed)
- Withdrawn / abandonedApr 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2010-059
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Midland 345kV
- Location
- Ector County, Texas
- Technology
- Gas: 516 MW
- Total requested
- 516 MW
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 December 2010
- Proposed online date
- April 2013
- Withdrawn
- April 2012
Location
Marker shows the centre of Ector County; the queue data does not give exact sites.
Other requests in Ector County
- Greyhound SolarSolar Β· 336 MW Β· agreement signed
- Sisters SolarSolar + storage Β· 302 MW Β· agreement signed
- Greyhound Solar - Phase ESolar Β· 151 MW Β· agreement signed
- Greyhound Solar - Phase FSolar Β· 102 MW Β· agreement signed
- Apple BESSBattery storage Β· 9.9 MW Β· agreement signed
- Gypsum Plains SolarSolar + storage Β· 503 MW Β· in study
- Velociraptor BESS IISolar + storage Β· 261 MW Β· in study
- Velociraptor BESS ISolar + storage Β· 261 MW Β· in study
- Van Zandt Energy StorageBattery storage Β· 257 MW Β· in study
- Velociraptor Solar IISolar + storage Β· 252 MW Β· in study
- Velociraptor Solar ISolar + storage Β· 252 MW Β· in study
- Gypsum Plains StorageSolar + storage Β· 211 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem