Completed queue projects in Texas (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown162,305 MW
Active in queue58.6 GW293 requests
Agreement signed23.9 GW116 requests
Withdrawn8117.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Frontera Energy Center
Gas Β· Frontera Generation Limited Partnership
524 MWOperating Hidalgo, TXERCOT Mar 20222023
Jarvis BESS
Other Β· SMT Ironman BESS LLC
308 MWOperating Brazoria, TXERCOT Mar 20222024
Photon Storage
Other Β· GulfStar Power, LLC
306 MWOperating Wharton, TXERCOT Jun 20222024
BoCo BESS
Other Β· BoCo BESS
156 MWOperating Borden, TXERCOT May 20222024
Photon BESS2 SLF
Other Β· GulfStar Power, LLC
153 MWOperating Wharton, TXERCOT Jun 20222024
Swift Air Solar
Solar Β· Swift Air Solar, LLC
147 MWOperating Ector, TXERCOT Nov 20222025
Wigeon Whistle BESS
Other Β· Wigeon Whistle BESS
123 MWOperating Collin, TXERCOT Apr 20222024
Black Springs BESS
Battery storage Β· Black Springs BESS LLC
121 MWOperating Palo Pinto, TXERCOT Apr 20222025
Al Pastor BESS
Other Β· Al Pastor BESS LLC
103 MWOperating Dawson, TXERCOT Mar 20222024
RABBS U7 U8 Power Station
Gas
102 MWOperating Fort Bend, TXERCOT May 20222022
Lucky Bluff BESS SLF
Battery storage Β· Lucky Bluff BESS LLC
101 MWOperating Erath, TXERCOT Mar 20222025
Noble Storage (BESS1)
Other
62.5 MWOperating Denton, TXERCOT Apr 20222022
XE Murat [Adlong] Storage
Battery storage Β· Liberty 1 Solar LLC
60.1 MWOperating Harris, TXERCOT Jun 20222025
Pyron Wind Repower
Onshore wind
19.9 MWOperating Nolan, TXERCOT Aug 20222024
Wharton BESS
Battery storage Β· I-eye Storage LLC
10.0 MWOperating Wharton, TXERCOT Nov 20222025
Farmersville West BESS 1
Other Β· HEN Infrastructure, LLC 1
9.9 MWOperating Collin, TXERCOT Nov 20222024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)