ONSHORE WIND · ERCOT

Pyron Wind Repower

Pyron Wind Repower is a 19.9 MW onshore wind request built and operating in the ERCOT interconnection queue, in Nolan County, Texas.

Queue statusOperating
  1. PlanningQueued Aug 2022 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0525
Grid region
ERCOT (Texas)
Location
Nolan County, Texas
Technology
Wind: 19.9 MW
Total requested
19.9 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
15 August 2022
Came online
June 2024

Location

Marker shows the centre of Nolan County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Nolan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem