Interconnection queue in South Carolina (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown404,533 MW
Active in queue4,533 MW40 requests
Agreement signed0.0 MW0 requests
Withdrawn695,046 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

40 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 957264, Anderson County
Gas
1,450 MWIn study Anderson, SCSoutheast Jun 2024
Gas project 956747, Rowan County
Gas
455 MWIn study Rowan, SCSoutheast Jun 2024
Solar project 957146, Newberry County
Solar
200 MWIn study Newberry, SCSoutheast Jun 2024
Solar project 267, Saluda County
Solar
186 MWIn study Saluda, SCSoutheast Jun 2024target 2028
Solar project 244, Williamsburg County
Solar
175 MWIn study Williamsburg, SCSoutheast Feb 2024target 2028
Solar project 270, Williamsburg County
Solar
150 MWIn study Williamsburg, SCSoutheast Jun 2024target 2029
Solar project 278, Williamsburg County
Solar
150 MWIn study Williamsburg, SCSoutheast Jun 2024target 2028
Solar project 962925, Lee County
Solar
145 MWIn study Lee, SCSoutheast Sep 2024
Hydro project 957349, Oconee County
Hydro
112 MWIn study Oconee, SCSoutheast Jun 2024
Solar project 266, Hampton County
Solar
100 MWIn study Hampton, SCSoutheast Jun 2024target 2028
Solar project 962635, Chesterfield County
Solar Β· Duke Energy Progress LLC
80.0 MWIn study Chesterfield, SCSoutheast Sep 2024
Solar project PP00007, Darlington County
Solar
75.0 MWIn study Darlington, SCSoutheast Dec 2024target 2027
Solar project 246, Williamsburg County
Solar
75.0 MWIn study Williamsburg, SCSoutheast Feb 2024target 2028
Solar project 956538, Marlboro County
Solar
75.0 MWIn study Marlboro, SCSoutheast Jun 2024
Battery storage project 251, Williamsburg County
Battery storage
75.0 MWIn study Williamsburg, SCSoutheast Feb 2024target 2028
Solar project PP00002, Darlington County
Solar
74.9 MWUnder construction Darlington, SCSoutheast Sep 2024target 2026
Solar project PP00004, Darlington County
Solar
74.9 MWIn study Darlington, SCSoutheast Sep 2024target 2027
Solar project 957368, Marlboro County
Solar
74.9 MWIn study Marlboro, SCSoutheast Jun 2024
Solar project 272, Orangeburg County
Solar
74.9 MWIn study Orangeburg, SCSoutheast Jun 2024target 2028
Solar project PP00003, Chesterfield County
Solar
74.9 MWUnder construction Chesterfield, SCSoutheast Sep 2024target 2027
Solar project 281, Aiken County
Solar
74.9 MWIn study Aiken, SCSoutheast Jun 2024target 2028
Solar project 962968, Marion County
Solar
74.9 MWIn study Marion, SCSoutheast Sep 2024
Solar project PP00001, Darlington County
Solar
74.2 MWUnder construction Darlington, SCSoutheast Sep 2024target 2028
Solar project 268, Richland County
Solar
51.0 MWIn study Richland, SCSoutheast Jun 2024target 2027
Solar project 956852, Darlington County
Solar
50.0 MWIn study Darlington, SCSoutheast Jun 2024
Solar project 963122, Laurens County
Solar
50.0 MWIn study Laurens, SCSoutheast Sep 2024
Solar project 261, Dillon County
Solar
49.9 MWIn study Dillon, SCSoutheast May 2024target 2025
Solar project 961214, Chesterfield County
Solar Β· Masked
48.0 MWIn study Chesterfield, SCSoutheast Sep 2024
Nuclear project 957233, York County
Nuclear
40.0 MWIn study York, SCSoutheast Jun 2024
Gas project 956475, Anderson County
Gas
30.0 MWIn study Anderson, SCSoutheast Jun 2024
Solar project 957086, Darlington County
Solar
30.0 MWIn study Darlington, SCSoutheast Jun 2024
Solar project 957449, Greenwood County
Solar
26.1 MWIn study Greenwood, SCSoutheast Jun 2024
Solar project 957084, Darlington County
Solar
25.0 MWIn study Darlington, SCSoutheast Jun 2024
Solar project 956528, Dillon County
Solar
9.0 MWIn study Dillon, SCSoutheast Jun 2024
Gas project 957517, Anderson County
Gas
5.0 MWIn study Anderson, SCSoutheast Jun 2024
Gas project 957514, Anderson County
Gas
5.0 MWIn study Anderson, SCSoutheast Jun 2024
Solar project 957087, Florence County
Solar
5.0 MWIn study Florence, SCSoutheast Jun 2024
Solar project 956532, Florence County
Solar
4.5 MWIn study Florence, SCSoutheast Jun 2024
Solar project 956497, Williamsburg County
Solar
1.9 MWIn study Williamsburg, SCSoutheast Jun 2024
Solar project 956474, Marion County
Solar
1.9 MWIn study Marion, SCSoutheast Jun 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)