🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › South Carolina

SOLAR · SOUTHEAST

Solar project 281, Aiken County

Solar project 281, Aiken County is a 74.9 MW solar request in interconnection study in the Southeast interconnection queue, in Aiken County, South Carolina, connecting to Santee Cooper.

Queue statusIn planning
  1. PlanningQueued Jun 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
281
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Santee Cooper
Location
Aiken County, South Carolina
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
2024 Cluster
Queue status
Active
Entered queue
5 June 2024
Proposed online date
June 2028

Location

Marker shows the centre of Aiken County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Aiken County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem