United States βΊ Grid βΊ Interconnection queues βΊ South Carolina
BATTERY STORAGE Β· SOUTHEASTBattery storage project 20230829018, Aiken County
Battery storage project 20230829018, Aiken County is a 200 MW battery storage request withdrawn in the Southeast interconnection queue, in Aiken County, South Carolina, connecting to Dominion Energy South Carolina.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20230829018
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Dominion Energy South Carolina
- Connection point (POI)
- Urquhart - SRS 230 kV
- Location
- Aiken County, South Carolina
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Proposed online date
- March 2026
Location
Marker shows the centre of Aiken County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Aiken County
- Solar project 124, Aiken CountySolar Β· 74.0 MW Β· under construction
- Solar project 20220316001, Aiken CountySolar Β· 80.0 MW Β· in study
- Solar project 208, Aiken CountySolar Β· 74.9 MW Β· in study
- Solar project 281, Aiken CountySolar Β· 74.9 MW Β· in study
- Gas project 20211118004, Aiken CountyGas Β· 65.9 MW Β· in study
- Gas project 20211118003, Aiken CountyGas Β· 64.9 MW Β· in study
- Gas project 305, Aiken CountyGas Β· 55.6 MW Β· in study
- Gas project 307, Aiken CountyGas Β· 55.6 MW Β· in study
- Gas project 306, Aiken CountyGas Β· 55.6 MW Β· in study
- Gas project 304, Aiken CountyGas Β· 55.6 MW Β· in study
- Solar project 45, Aiken CountySolar Β· 75.0 MW Β· built
- Solar project 20171013002, Aiken CountySolar Β· 151 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem