United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

OCTARY USA Β· INTERCONNECTION QUEUES

Onshore wind interconnection queue in Oregon

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3810.2 GW
Active in queue10.2 GW38 requests
Agreement signed0.0 MW0 requests
Withdrawn22831.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

38 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 10-037, Gilliam County
Onshore wind
500 MWPaused / redesign Gilliam, ORWest Aug 2010target 2015
Onshore wind project G0861, Deschutes County
Onshore wind
500 MWIn study Deschutes, ORWest Apr 2023target 2027
Onshore wind project G0619, Wasco County
Onshore wind
500 MWIn study Wasco, ORWest Apr 2019target 2023
Onshore wind project G0870, Lake County
Onshore wind
500 MWIn study Lake, ORWest Jun 2023target 2028
Onshore wind project G0871, Lake County
Onshore wind
500 MWIn study Lake, ORWest Jun 2023target 2028
Onshore wind project G0344, Gilliam County
Onshore wind
488 MWIn study Gilliam, ORWest Sep 2008target 2024
Onshore wind project 09-035, Gilliam County
Onshore wind
401 MWPaused / redesign Gilliam, ORWest Jul 2009target 2013
Onshore wind project 11-043, Umatilla County
Onshore wind
400 MWPaused / redesign Umatilla, ORWest Jun 2011target 2014
Onshore wind project 10-036, Sherman County
Onshore wind
400 MWPaused / redesign Sherman, ORWest Mar 2010target 2014
Onshore wind project 07-023, Jefferson County
Onshore wind
375 MWPaused / redesign Jefferson, ORWest Sep 2007target 2012
Onshore wind project 07-022, Jefferson County
Onshore wind
375 MWPaused / redesign Jefferson, ORWest Sep 2007target 2012
Onshore wind project G0366, Morrow County
Onshore wind
302 MWIn study Morrow, ORWest May 2009target 2014
Onshore wind project G0918, Lane County
Onshore wind
300 MWIn study Lane, ORWest Aug 2023target 2029
Onshore wind project G0972, Curry County
Onshore wind
300 MWIn study Curry, ORWest Oct 2023target 2029
Onshore wind project G0994, Sherman County
Onshore wind
277 MWIn study Sherman, ORWest Nov 2023target 2028
Onshore wind project G1013, Umatilla County
Onshore wind
250 MWIn study Umatilla, ORWest Nov 2023target 2030
Onshore wind project 23-226, Jefferson County
Onshore wind
250 MWIn study Jefferson, ORWest Mar 2023target 2027
Onshore wind project 23-227, Jefferson County
Onshore wind
250 MWIn study Jefferson, ORWest Mar 2023target 2029
Onshore wind project 23-228, Jefferson County
Onshore wind
250 MWIn study Jefferson, ORWest Mar 2023target 2029
Onshore wind project 23-231, Jefferson County
Onshore wind
250 MWIn study Jefferson, ORWest Mar 2023target 2027
Onshore wind project G0974, Wasco County
Onshore wind
250 MWIn study Wasco, ORWest Oct 2023target 2029
Onshore wind project G0640, Klamath County
Onshore wind
239 MWIn study Klamath, ORWest Feb 2020target 2025
Onshore wind project G0435, Morrow County
Onshore wind
238 MWIn study Morrow, ORWest Aug 2010target 2013
Onshore wind project G1036, Hood River County
Onshore wind
234 MWIn study Hood River, ORWest Nov 2023target 2028
Onshore wind project G0362, Gilliam County
Onshore wind
204 MWIn study Gilliam, ORWest Apr 2009target 2012
Onshore wind project G0363, Gilliam County
Onshore wind
204 MWIn study Gilliam, ORWest Apr 2009target 2012
Onshore wind project G0345, Wasco County
Onshore wind
201 MWIn study Wasco, ORWest Sep 2008target 2010
Onshore wind project 11-040, Gilliam County
Onshore wind
200 MWPaused / redesign Gilliam, ORWest Mar 2011target 2015
Onshore wind project 09-033, Wasco County
Onshore wind
200 MWPaused / redesign Wasco, ORWest Jan 2009target 2013
Onshore wind project 11-039, Gilliam County
Onshore wind
200 MWPaused / redesign Gilliam, ORWest Mar 2011target 2015
Onshore wind project G0980, Sherman County
Onshore wind
191 MWIn study Sherman, ORWest Nov 2023target 2028
Onshore wind project G1074, Gilliam County
Onshore wind
111 MWIn study Gilliam, ORWest Feb 2025target 2027
Onshore wind project G0867, Sherman County
Onshore wind
100 MWIn study Sherman, ORWest Jun 2023target 2027
Onshore wind project G0917, Gilliam County
Onshore wind
90.3 MWIn study Gilliam, ORWest Aug 2023target 2025
Onshore wind project 12-053, Polk County
Onshore wind
87.5 MWPaused / redesign Polk, ORWest Oct 2012target 2015
Onshore wind project G1012, Umatilla County
Onshore wind
67.0 MWIn study Umatilla, ORWest Nov 2023target 2030
Onshore wind project G0827, Sherman County
Onshore wind
25.0 MWIn study Sherman, ORWest Dec 2022target 2024
Onshore wind project G0975, Umatilla County
Onshore wind
19.0 MWIn study Umatilla, ORWest Oct 2023target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)