United States › Grid › Interconnection queues › Oregon
OCTARY USA · INTERCONNECTION QUEUESCompleted queue projects in Oregon
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Shepherds Flat Onshore wind · Shepherds Flat Wind, LLC |
750 MW | |
| Biglow Canyon Wind Onshore wind |
600 MW | |
| Carty CCCT Gas |
464 MW | |
| Klondike 3 Wind Onshore wind · Klondike Wind Power III, LLC |
300 MW | |
| Ella Wind 3 Onshore wind · Wheatridge Wind Energy, LLC |
300 MW | |
| Goldendale Energy Center Gas · Goldendale Energy Center, LLC |
247 MW | |
| Gas project 07-025, Columbia County Gas |
225 MW | |
| Gas project 11-041, Columbia County Gas |
225 MW | |
| Hydro project 757, Baker County Hydro · Idaho Power Company - Power Supply |
220 MW | |
| Montague I Onshore wind · Avangrid Power, LLC |
202 MW | |
| Montague 2 Solar · Avangrid Power, LLC |
202 MW | |
| Hay Canyon/Star Point Onshore wind · Avangrid Power, LLC |
201 MW | |
| Battery storage project 17-066, Multnomah County Battery storage |
200 MW | |
| Battery storage project 19-076, Multnomah County Battery storage |
200 MW | |
| Arlington Wind_Wheatfield Wind Onshore wind · EDP Renewables North America LLC |
200 MW | |
| Iberdrola Renewables Inc Onshore wind · Avangrid Power, LLC |
200 MW | |
| Leaning Juniper II Onshore wind · Avangrid Power, LLC |
200 MW | |
| Battery storage project 20-082, Washington County Battery storage |
200 MW | |
| Pebble Springs Wind Project Onshore wind · Avangrid Power, LLC |
200 MW | |
| Onshore wind project 120, Union County Onshore wind |
101 MW | |
| White Creek Onshore wind · Harvest Wind Project |
100 MW | |
| Gas project 6, Klamath County Gas · PPM Energy, Inc. |
100 MW | |
| Shepherds Flat Wind Farm addition Onshore wind · Shepherds Flat Wind, LLC |
96.0 MW | |
| Stateline Wind Farm Onshore wind · FPL Energy Vansycle L.L.C. |
90.0 MW | |
| Blueridge Solar/Battery Project Solar + storage · Wheatridge Solar Energy Center, LLC |
80.0 MW | |
| Willow Creek and Horn Butte Onshore wind · Invenergy Wind Development LLC |
72.0 MW | |
| Combine Hills II Onshore wind · Eurus Combine Hills II LLC |
63.0 MW | |
| Solar project 850, Crook County Solar · Millican Solar Energy LLC |
60.8 MW | |
| Solar project 594, Crook County Solar · Solar Star Oregon II, LLC |
56.0 MW | |
| Solar project 721, Klamath County Solar · Skysol, LLC |
55.0 MW | |
| Biglow Canyon Wind Farm Addition Onshore wind |
50.0 MW | |
| Klondike 2 Wind Onshore wind · Klondike Wind Power II, LLC |
50.0 MW | |
| Solar project 729, Lake County Solar · Airport Solar, LLC |
47.3 MW | |
| Gas project 12-050, Columbia County Gas |
44.0 MW | |
| Coyote Springs 2 Gas |
42.0 MW | |
| Onshore wind project 17, Umatilla County Onshore wind · Eurus Combine Hills I, LLC |
41.0 MW | |
| Solar project 621, Crook County Solar · Invenergy Solar Development, LLC |
40.0 MW | |
| Onshore wind project 650, Umatilla County Onshore wind · Oregon Wind Farms, LLC |
40.0 MW | |
| Geothermal project 179, Malheur County Geothermal |
36.0 MW | |
| Carty CCCT Gas |
36.0 MW | |
| Other project 151, Jackson County Other · Biomass One, LP |
30.0 MW | |
| Klondike 1 Wind Onshore wind · Northwestern Wind Power, LLC |
26.0 MW | |
| Hydro project 68, Klamath County Hydro · PacifiCorp Commercial & Trading |
25.0 MW | |
| Condon Wind Farm Onshore wind · Seawest Windpower, Inc. |
25.0 MW | |
| Klondike Wind Power Onshore wind · Klondike Wind Power, LLC |
24.0 MW | |
| Other project 5, Douglas County Other · Roseburg Forest Products Inc. |
20.0 MW | |
| NewSun Riley Project Solar · Riley Interconnection LLC |
20.0 MW | |
| NewSun Starvation Solar Project Solar · NewSun Energy Transmission Company LLC |
20.0 MW | |
| NewSun Fort Rock Project Solar · NewSun Energy Transmission Company LLC |
20.0 MW | |
| Fort Rock II Solar · Fort Rock Interconnection II LLC |
20.0 MW |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)