Arlington Wind_Wheatfield Wind is a 200 MW onshore wind request built and operating in the West interconnection queue, in Gilliam County, Oregon, connecting to EDP Renewables North America LLC.

Queue statusOperating
  1. PlanningQueued Feb 2002 (completed)
  2. ConsentedAug 2008 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G95
Grid region
West (non-ISO utilities)
Utility / transmission owner
EDP Renewables North America LLC
Developer
EDP Renewables North America LLC
Connection point (POI)
Jones Canyon Substation
Location
Gilliam County, Oregon
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
on-line November 2008 for 103 MW and February 2009 for 93 MW (LGIA split)
Queue status
Operational
Entered queue
15 February 2002
Agreement signed
29 August 2008
Proposed online date
October 2008

Location

Marker shows the centre of Gilliam County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Gilliam County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem