Solar project 729, Lake County

Solar project 729, Lake County is a 47.3 MW solar request built and operating in the West interconnection queue, in Lake County, Oregon, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Feb 2016 (completed)
  2. ConsentedAug 2017 (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
729
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Airport Solar, LLC
Connection point (POI)
Alturas-Mile Hi transmission line
Location
Lake County, Oregon
Technology
Solar: 47.3 MW
Total requested
47.3 MW
Service type
Energy only (ERIS)
Study phase
IA signed 8/15/17, includes Q0780
Queue status
Operational
Entered queue
26 February 2016
Agreement signed
15 August 2017
Proposed online date
November 2019

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.